Daily Progress Reports ingested from engineer mobile app · AI quality & material flags
63.2%
Overall Progress
across 2 active towers
160
Site Labour
T1 84 · T2 76
217 m³
Concrete cast (wk)
2.1% under budget
3
AI Flags
2 material · 1 safety
Baseline vs. actual — variance auto-flagged against India Real Estate (RERA) timelines
Foundation & PCC
Completed 2026-02-11
100% complete
Podium + Ground Floor
Completed 2026-04-18
100% complete
Structure up to Floor 3
Completed 2026-07-06
100% complete
Structure up to Floor 5
Planned 2026-09-28
68% complete
External & Facade Works
Planned 2026-11-15
12% complete
MEP Rough-in
Planned 2026-12-05
0% complete
Tower T1
2 days ahead68.4% structural progress
Labour
84
Concrete
42 m³
Tower T2
0 days ahead61.2% structural progress
Labour
76
Concrete
35 m³
AI Site Agent · material flag
Cement stock at Tower 2 below reorder level. Purchase order auto-raised and routed for approval on the finance module.
Ingested at site close-out · photos + notes + labour + concrete
| Date | Tower | Progress | Labour | Concrete | Engineer Note | |
|---|---|---|---|---|---|---|
| 2026-08-05 | TT1 | 68.4% | 84 | 42 m³ | Level 5 slab shutter work in progress. 2 days ahead of schedule. | |
| 2026-08-04 | TT1 | 67.9% | 82 | 38 m³ | Steel fixing for slab completed on east wing. | |
| 2026-08-04 | TT2 | 61.2% | 76 | 35 m³ | Blockwork level 3 ongoing; cement stock low — RFQ raised. | |
| 2026-08-03 | TT1 | 67.4% | 88 | 44 m³ | Level 4 slab cast completed. | |
| 2026-08-03 | TT2 | 60.8% | 74 | 33 m³ | Site photos uploaded; AI flagged material shortage for plaster. |